KSC Release No. 17-00
NASA will begin the countdown for launch of Space Shuttle Endeavour on mission The countdown includes 24 hours of built-in hold time leading to a launch time at STS-99 is the first Space Shuttle mission of 2000, the 14th flight of the orbiter Endeavour rolled out of Kennedy Space Centerís Orbiter Processing Facility bay on On mission STS-99, Endeavour and crew will capture the most accurate elevation The STS-99 crew includes: Commander Kevin Kregel, Pilot Dom Gorie, Mission The crew returned to KSC at about noon on Feb. 7. Their activities at KSC prior to
KSC Contact: Joel Wells
STS-99 Feb. 8, at 5:30 p.m. EST at the T-43 hour mark. The KSC launch team will conduct
the countdown from Firing Room 3 of the Launch Control Center.
12:30 p.m. on Feb. 11. The launch window extends for 2 hours and 10 minutes.
Endeavour and the 97th flight overall in NASAís Space Shuttle program. STS-99 is
scheduled to last 11 days, 4 hours, and 8 minutes with a planned KSC landing at 4:38 p.m.
on Feb. 22.
Dec. 2, 1999, and was mated with the external tank and solid rocket boosters in the Vehicle
Assembly Building. The complete Shuttle stack was transported to Pad 39A on Dec. 13.
Following a launch postponement on Jan. 31 due to bad weather, Shuttle workers replaced
Endeavourís faulty master events controller No. 2 located in the aft engine compartment.
With prelaunch preparations now complete, Endeavour stands ready for Fridayís launch.
measurements of the Earthís surface ever attained. Using a unique radar system dubbed
Shuttle Radar Topography Mission (SRTM), STS-99 will glean valuable 3-D mapping
images for application in fields ranging from military planning to back country recreation.
Specialists Janet Kavandi, Janice Voss, Mamoru Mohri, and Gerhard Thiele.
launch will include crew equipment fit checks, medical examinations and opportunities to fly
in the Shuttle Training Aircraft.
*all times are Eastern
Launch – 3 Days (Tuesday, Feb. 8)
- Prepare for the start of the STS-99 launch countdown
- Perform the call-to-stations (5 p.m.)
- Countdown begins at the T-43 hour mark (5:30 p.m.)
- Begin final vehicle and facility close-outs for launch
- Check out back-up flight systems
- Review flight software stored in mass memory units and display systems
- Load backup flight system software into Endeavourís general purpose computers
- Remove mid-deck and flight-deck platforms (1:30 a.m.)
- Activate and test navigational systems
- Complete preparations for loading of power reactant storage and distribution system
- Middeck and flight deck preliminary inspections complete (9:30 a.m.)
Enter first built-in hold at T-27 hours for duration of 4 hours (9:30 a. m.)
- Clear launch pad of all non-essential personnel
- Perform test of the vehicle’s pyrotechnic initiator controllers (10:30 a.m.)
Resume countdown (1:30 p.m.)
- Begin operations to load cryogenic reactants into Endeavourís fuel cell storage tanks (1:30 ñ 9:30 p.m.)
Enter 4-hour built-in hold at T-19 hours (9:30 p.m.)
- Begin filling pad sound suppression system water tank
- Demate orbiter mid-body umbilical unit (10 p.m.)
- Resume orbiter and ground support equipment close-outs
- Pad sound suppression system water tank filled (1:30 a.m.)
Resume countdown (1:30 a.m.)
- Start final preparations of the Shuttle’s three main engines for main propellant tanking and flight
- Install mission specialists’ seats in crew cabin begins (3:30 a.m.)
- Close-out the tail service masts on the mobile launcher platform
Enter planned hold at T-11 hours for 12 hours, 40 minutes (9:30 a.m.)
- Begin startracker functional checks (10:30 a.m.)
- Activate orbiter’s inertial measurement units
- Activate the orbiter’s communications systems
- Install film in numerous cameras on the launch pad (1:30 p.m.)
- Flight crew equipment late stow (2 p.m.)
- Move Rotating Service Structure (RSS) to the park position (6:30 p.m.)
- Perform ascent switch list
Resume countdown (10:10 p.m.)
- Fuel cell flow-through purge complete
- Activate the orbiter’s fuel cells (11:20 p.m.)
- Clear the blast danger area of all non-essential personnel
- Switch Endeavourís purge air to gaseous nitrogen (12:25 a.m.)
Enter planned 1-hour built-in hold at the T-6 hour mark (3:10 a.m.)
- Launch team verifies no violations of launch commit criteria prior to cryogenic
loading of the external tank (3:15 a.m.) - Clear pad of all personnel
- Chilldown of propellant transfer lines
- Begin loading the external tank with about 500,000 gallons of cryogenic propellants (about 4:10 a.m.)
Resume countdown (4:10 a.m.)
- Complete filling the external tank with its flight load of liquid hydrogen and liquid oxygen propellants (about 7:10 a.m.)
- Final Inspection Team proceed to launch pad
Enter planned 2-hour built-in hold at T-3 hours (7:10 a.m.)
- Perform inertial measurement unit preflight calibration
- Align Merritt Island Launch Area (MILA) tracking antennas
- Perform open loop test with Eastern Range
Resume countdown at T-3 hours (9:10 a.m.)
- Crew departs Operations and Checkout Building for the pad (9:15 a.m.)
- Complete close-out preparations in the white room
- Check cockpit switch configurations
- Flight crew begins entry into the orbiter (about 9:45 a.m.)
- Astronauts perform air-to-ground voice checks with Launch and Mission Control
- Close Endeavourís crew hatch (about 11 a.m.)
- Begin Eastern Range final network open loop command checks
- Perform hatch seal and cabin leak checks
- Complete white room close-out
- Close-out crew moves to fallback area
- Primary ascent guidance data is transferred to the backup flight system
Enter planned 10-minute hold at T-20 minutes (11:50 a.m.)
- NASA Test Director conducts final launch team briefings
- Complete inertial measurement unit pre-flight alignments
Resume countdown (12 noon)
- Transition the orbiter’s onboard computers to launch configuration
- Start fuel cell thermal conditioning
- Close orbiter cabin vent valves
- Transition backup flight system to launch configuration
Enter planned 10-minute hold at T-9 minutes (12:11 p.m.)
- Launch Director, Mission Management Team and NASA Test Director conduct final polls for go/no go to launch
Resume countdown at T-9 minutes (12:21 p.m.)
- Start automatic ground launch sequencer (T-9:00 minutes)
- Retract orbiter crew access arm (T-7:30)
- Start mission recorders (T-6:15)
- Start Auxiliary Power Units (T-5:00)
- Arm SRB and ET range safety safe and arm devices (T-5:00)
- Start liquid oxygen drainback (T-4:55)
- Start orbiter aerosurface profile test (T-3:55)
- Start main engine gimbal profile test (T-3:30)
- Pressurize liquid oxygen tank (T-2:55)
- Begin retraction of the gaseous oxygen vent arm (T-2:55)
- Fuel cells to internal reactants (T-2:35)
- Pressurize liquid hydrogen tank (T-1:57)
- Deactivate SRB joint heaters (T-1:00)
- Orbiter transfers from ground to internal power (T-0:50 seconds)
- Ground Launch Sequencer go for auto sequence start (T-0:31 seconds)
- SRB gimbal profile (T-0:21 seconds)
- Ignition of three Space Shuttle main engines (T-6.6 seconds)
- SRB ignition and liftoff (T-0)
SUMMARY OF BUILT-IN HOLDS FOR STS-99 |
|||
---|---|---|---|
T-TIME | LENGTH OF HOLD | HOLD BEGINS | HOLD ENDS |
T-27 hours | 4 hours | 9:30 a.m. Wed. | 1:30 p.m. Wed. |
T-19 hours | 4 hours | 9:30 p.m. Wed. | 1:30 a.m. Thurs. |
T-11 hours | 12 hours, 40 minutes | 9:30 a.m. Thurs. | 10:10 p.m. Thurs. |
T-6 hours | 1 hour | 3:10 a.m. Fri. | 4:10 a.m. Fri. |
T-3 hours | 2 hours | 7:10 a.m. Fri. | 9:10 a.m. Fri. |
T-20 minutes | 10 minutes | 11:50 a.m. Fri. | 12:00 p.m. Fri. |
T-9 minutes | 10 minutes | 12:11 p.m. Fri. | 12:21 p.m. Fri. |
CREW FOR MISSION STS-99 | |
---|---|
POSITION | NAME |
Commander (CDR) | Kevin Kregel |
Pilot (PLT) | Dom Gorie |
Mission Specialist (MS1) | Gerhard Thiele |
Mission Specialist (MS2) | Janet Kavandi |
Mission Specialist (MS3) | Janice Voss |
Mission Specialist (MS4) | Mamoru Mohri |
SUMMARY OF STS-99 LAUNCH DAY CREW ACTIVITIES Friday, Feb. 11 |
|
---|---|
12:15 a.m. | Wake up Blue Team (PLT, MS3 and MS4) |
12:45 a.m. | Blue Team breakfast |
6:30 a.m. | Wake up Red Team (CDR, MS1 and MS2) |
8:00 a.m.* | Blue Team lunch/Red Team breakfast and photo |
8:35 a.m. | Weather briefing (CDR, PLT, MS2) |
8:35 a.m.* | Don launch and entry suits (MS1, MS3 & MS4) |
8:45 a.m.* | Don launch and entry suits (CDR, PLT, MS2) |
9:15 a.m.* | Depart for Launch Pad 39A |
9:45 a.m.* | Arrive at white room and begin ingress |
11:00 a.m.* | Close crew hatch |
12:30 p.m.* | Launch |
*Televised events (times may vary slightly)