ISS
Controllers maneuvered the International Space Station Sept. 22 to avoid a close approach by debris from the upper stage of a Japanese rocket. Credit: NASA

Updated March 5 with NASA comment.

WASHINGTON — NASA has sharply increased the prices it charges commercial users of the International Space Station for cargo and other resources, a move that has left some companies confused and frustrated.

NASA announced Feb. 25 that it was revising the commercial marketing pricing policy it first published in June 2019 as part of a new low Earth orbit commercialization strategy. That policy, which set aside a fraction of station resources for commercial applications beyond research and development, included a price list for resources such as cargo to and from the station and crew time to carry out work.

In the statement, published with little fanfare on the agency’s website, NASA said it was updating that price list “to reflect full reimbursement for the value of NASA resources.” The decision to do so, NASA said, was based on “discussions with stakeholders, the current market growth, and in anticipation of future commercial entities capable of providing similar services.”

By removing the subsidy, the prices of those services went up significantly. The cost to transport one kilogram of cargo up to the station, known as “upmass,” went from $3,000 to $20,000. The cost to bring that one kilogram back down from the station, “downmass,” went from $6,000 to $40,000. One hour of crew member time, previously $17,500, is now $130,000.

The sudden change in prices, which took effect immediately, took some ISS users by surprise. An executive with one company, who spoke on background because that company is still evaluating the impacts of the pricing change, was not aware of NASA’s decision to raise prices until contacted by SpaceNews.

“NASA has not done a good job communicating with the stakeholders,” said Jeffrey Manber, chief executive of Nanoracks. “We are in discussions with customers and suddenly we are being notified of a major increase.”

That sudden increase in prices, he said, forced Nanoracks to suspend discussions with two potential customers, who he said were “priced out of their budget” by the increase.

Another executive, speaking on background, was not aware of any discussion by NASA about changing the pricing policy ahead of the announcement. The increase, the executive said, could lead some customers to seek alternatives.

NASA didn’t elaborate in its original statement on its decision to go to what it calls “full value” pricing beyond its statement. Manber said such a change should have been first discussed by the NASA Advisory Council’s Regulatory and Policy Committee, on which he serves, but that the issue had not come up at its meetings.

In a statement to SpaceNews March 5, NASA said it stated on the pricing policy page on its website Jan. 26 that prices were under review, and notified companies that had submitted “Commercial Use” proposals that prices would soon be adjusted. “Nearly two years have passed since NASA released the initial pricing policy,” the agency stated. “The pricing policy from June 2019 did not reflect full reimbursement for the value of NASA resources; it was intended to stimulate the market and was planned to be adjusted.”

Manber said that NASA may be reacting to language in a report accompanying the final fiscal year 2021 appropriations bill, which provided NASA with just $17 million for LEO commercialization efforts, compared to its request of $150 million. The report instructed NASA to provide Congress data on projects selected through its LEO commercialization effort on the station, the total costs incurred by NASA for the delivery and execution of them, and how much NASA will be reimbursed.

The report also prohibited NASA from using funding “to subsidize the cost of any project that is primarily intended for marketing, advertising, or entertainment purposes.” That appeared in reaction to criticism the agency faced for some commercial ISS initiatives, like flying Estée Lauder cosmetics to the station for a photo shoot or the possibility of filming a movie starring actor Tom Cruise on the station.

Manber argued that NASA should “fine tune” the pricing policy, charging full price for those marketing and entertainment activities but continuing to subsidize resources for other commercial work, such as those activities that also have an education angle. “I believe there are commercial projects, along with education efforts and partners, that bring value to the International Space Station. They show American leadership,” he said. “There’s a nuanced discussion that needs to be made with Congress and NASA.”

In its statement, NASA noted that “there has been a solid demand for commercial and marketing activities from both traditional aerospace companies and from novel industries.” However, it said that while it considered an “interim” pricing update that still offered some subsidization of prices, the report language “is clear that no appropriated funds could be used to subsidize certain commercial use activities. Thus, less than full reimbursement was determined to be inconsistent with the report language.”

NASA added that the pricing policy applies only to commercial activities on the station. “Other activities that are educational in nature, or scientific or research and development, can and should fly via the International Space Station U.S. National Laboratory. There is no change to process or costs for these activities.”

The LEO commercialization policy also enabled private astronaut missions to the ISS, and provided a price list for resources such missions would need. That included $22,500 per person per day for crew supplies and $11,250 per person per day for life support.

The revised list no longer includes any prices for services for private astronaut missions. “NASA is in the process of reassessing the value and amount of available resources for private astronaut missions and plans to update that pricing policy in the near future,” the agency stated.

Axiom Space, which is flying a four-person private astronaut mission to the station in early 2022, is not concerned about any potential changes in prices. “Axiom was never relying on NASA to provide all the services they had listed, so this development would not affect us,” company spokesperson Beau Holder said. “It is Axiom’s intent to take care of itself and its crews on orbit.”

Manber said he hopes that the revised policy is not the final word from NASA on the issues. “I’m hopeful that this is the beginning of a dialogue on more mature support for commercialization.”

Jeff Foust writes about space policy, commercial space, and related topics for SpaceNews. He earned a Ph.D. in planetary sciences from the Massachusetts Institute of Technology and a bachelor’s degree with honors in geophysics and planetary science...