PARIS -- NASA has suspended Lockheed Martin's contract to build
the GOES-R meteorological satellites following Boeing's second protest of the
award, NASA said May 21. The U.S. Government Accountability Office (GAO) has up
to 100 days, to late August, to issue a ruling.
In an e-mail response to Space News inquiries, NASA spokesman
Stephen Cole said NASA has issued a "stay of contract performance" order to
Lockheed Martin following Boeing's May 18 protest.
"Once a stay of contract performance is issued, all work under
the contract stops," Cole said. "Thus, there could be schedule slippages with
program milestones since no work is being performed." The first of the GOES-R
satellites had been scheduled for launch in 2015.
Chicago-based Boeing filed its original GAO protest in late
2008 following NASA's decision. The contract was suspended for what was
expected to be GAO's customary 100-day review.
But midway through the GAO examination, NASA agreed to "re-
evaluate" its decision. "[A]s a result of that process, a series of corrective
actions were implemented," NASA said in a May 7 announcement saying it and the
U.S. National Oceanic and Atmospheric Administration (NOAA) had reaffirmed the
initial choice of Lockheed Martin Space Systems as GOES-R prime contractor.
Cole declined to detail what corrective actions NASA took to improve its bid
evaluation.
The contract is for two satellites with options for two more,
with a total value, assuming the options are exercised, of $1.09 billion.
In a May 19 statement, Boeing said the NASA decision includes
"serious flaws and a lack of transparency in the selection process."
Boeing's protest appears to go beyond questioning the technical
merits of Lockheed Martin's GOES-R bid to raising questions about NASA's basic
fairness in evaluating the bids.
In a May 19 e-mail, Boeing spokesman Joseph J. Tedino said Boeing has reason to believe it rated higher
than Lockheed Martin in NASA's evaluation, and that "NASA inexplicably changed
the scores" during the initial evaluation in 2008. "These scores involved the
mission-suitability factors — which are the most important factors in the
selection process — and switched the positions of Boeing and Lockheed Martin in
the competition."
NASA's Cole declined to address that point, saying it is now
subject to an ongoing GAO review and under a "GAO protective order," meaning
NASA cannot comment publicly on it.
Boeing also alleges that "certain documents related to the
initial evaluation were destroyed." Cole said that, too, is covered by the
protective order.
In a one-page summary of the original grounds for the protest,
Boeing's legal counsel, Cooley Godward Kronish LLP of Washington, said NASA never explained in
detail how it arrived at its decision — in part because the agency routinely destroys
documents relating to its evaluation process.
"NASA relies upon an evaluation process that generates the
minimum possible record of its evaluation, and then destroys all but the
highest level of documentation after the source selection is made," the law
firm said in its summary. "Regardless of the questionable merits of such a
process, in this case it appears that NASA may have elected to hide certain
events that were not consistent with the story it wanted to tell GAO and
Boeing, and now it has no contemporaneous record to support the reasonableness
of its actions."
The law firm also said that NASA's public explanation of its
original decision — that Lockheed Martin received a slightly better score than
Boeing on technical merits — was subsequently found to be untrue.
Acting in response to Boeing and GAO pressure to explain the
decision, NASA provided documents that the law firm said appear to show Boeing
as the winner on technical merit.
"[W]ithout any record evidence whatsoever
to explain either the process used or the basis for the rescoring — NASA
reduced Boeing's score... [and] increased Lockheed
Martin's score," according to the Boeing legal team.
The legal team's summary does not address the issue of whether
Lockheed Martin did in fact best Boeing on price. NASA had found Lockheed's bid
to be 6 percent less costly than Boeing's. Tedino's
May 19 e-mail said Boeing has concluded that "our cost estimate is more
believable because we built GOES N, O and P, which were used as the basis for
the GOES-R price."
Boeing's GAO protest is also based on the fact that NASA has
not explained its decision in detail to Boeing or granted Boeing's request for
face-to-face meetings.
In the NASA statement, Cole said: "Federal Acquisition
Regulation (FAR) provides that debriefings may be done orally or in writing.
Boeing was provided an oral debriefing after the initial award in December
2008. That debriefing was over three hours long and covered all aspects of
Boeing's proposal. The written debriefing NASA provided Boeing for the new
evaluation provided Boeing all the information required to be disclosed by the
FAR and also responded to all the questions that Boeing submitted to NASA."
Tedino confirmed that Boeing received
a NASA letter May 21, but he said the letter "does not adequately explain" the
decision.
A separate contract for the GOES-R ground system will be
announced this year. NASA's Goddard Space Flight Center in Greenbelt,
Md., is overseeing the GOES-R acquisition
with funds from NOAA, which operates the satellites. In its May 19 statement,
Boeing said it has filed only two GAO protests since 2000 — for GOES-R and for
a contract to build U.S. Air Force aerial refueling tankers. A lengthy GAO
review of the tanker award concluded that Boeing was correct in alleging that
the tanker selection process was flawed.